76% progress in construction of 2 Platforms of Phase 14 of South Pars
EghtesadOnline: Operator of the project for development of phase 14 of South Pars gas field Morteza Zarringol says the project for construction of platforms A and B of phase 14 of South Pars has shown 76 percent progress.
Zarringol said the two platforms will be operational and installed in January and March.
He said due to high progress in construction of the platforms and thanks to wise management of the prioritized projects by the Ministry of Petroleum, the platforms C14 and D14 construction was taken into consideration within contexts of the prioritized phases of 17 and 18.
He added that the satellite platforms of B17 and B18 were also considered within framework of phase 14 last year, reports IRNA.
He said operations to fix the platform D14, where platform B18 is located, ended in Mordad.
The official went on to say other satellite platforms of the phase will be soon prepared for loading and installation where the B17 platform is located.
He concluded that for the time being, operations for construction of the platforms A and B in Persian Gulf yard for the phase 14 of South Pars gas field has shown 76 percent progress.